Hi Mr. Nelson:
      I've enclosed several photos of the construction of Mood's Covered Bridge. I'll send you some more photos as the work progresses.
      In some of the November 5th shots, you can see the other truss still laying on its side on the deck.
      Since I live so close to Mood's bridge (walking distance), I go to check on it at least twice a week or more. When I was there this past Sunday, not much had changed from the November 8th photos, but when I stopped there very late yesterday afternoon, they had the rafters finished and were starting to cover them, so I'll try to get down there today to get more photos.
      I don't want to miss anything.
            Happy Bridging, Doris Taylor

All photos by Doris Taylor
Mood's Bridge. Photo by Doris Taylor September 23, 2007 Mood's Bridge. Photo by Doris Taylor September 28, 2007
Mood's Bridge.
September 23, 2007
Mood's Bridge.
September 28, 2007
Mood's Bridge. Photo by Doris Taylor October 9, 2007 Mood's Bridge. Photo by Doris Taylor November 5, 2007
Mood's Bridge.
October 9, 2007
Mood's Bridge.
November 5, 2007
Mood's Bridge. Photo by Doris Taylor November 5, 2007 Mood's Bridge. Photo by Doris Taylor November 5, 2007
Mood's Bridge.
November 5, 2007
Mood's Bridge.
November 5, 2007
Mood's Bridge. Photo by Doris Taylor November 8, 2007 Mood's Bridge. Photo by Doris Taylor November 8, 2007
Mood's Bridge.
November 8, 2007
Mood's Bridge.
November 8, 2007
Moods's Bridge. Photo by Doris Taylor November 8, 2007 Moods's Bridge. Photo by Doris Taylor November 8, 2007
Mood's Bridge.
November 8, 2007
Mood's Bridge.
November 8, 2007